Project Description:
In June 2013 Powell Engineering were awarded the first stage of a 132 kV project for Electricity North West (ENW). In conjunction with the replacement of 132 kV Grid Transformers, PEL were responsible for the installation of associated plant and equipment
Our remit was:
This would entail;
The refurbishment works was undertaken with limited space within a compact compound, adjacent live circuits and 132kV overhead lines. Independent contractors were also present working in parallel to our works. It was essential to build a close working relationship with these contractors to ensure a safe and efficient working environment.
Intricate planning and financial control meant that a smooth cash flow was maintained throughout. All aspects of management for the project including, procurement, HS&E and Quality control was run from our Doncaster Office. Throughout the works and on completion of the project Powell Engineering received excellent feedback from the client acknowledging our excellent health & safety performance along with high standards and quality of the workmanship.
We have recently been awarded stage two of the project which is due to commence early 2014