The new ESB Networks Ardnagappary 110/38kV Substation is located outside Bunbeg, Co. Donegal.
Omexom scope was the Electrical installation of:
a new 110/38 kV tail fed substation consisting of a single 110 kV AIS line/transformer bay
a 31.5 MVA 110/38 kV transformer
an Arc Suppression Coil
a 38 kV GIS busbar
a 38 kV GIS incomer transformer bay
a 38 kV GIS incomer line bay (Gate 3)
2 No. 38 kV GIS feeder bays
a 38 kV GIS outgoer transformer bay and associated control building.
During Phase 1 (Civils works) Omexom was also responsible for the Electrical fit-out of the substation building ahead of electrical installation.