Killin Update
Our Substations team have been hard at work up at the 132/33kV substation in Killin playing their part in SSEN's VISTA project. The team are converting and upgrading the existing outdoor bays to facilitate the new underground 132kV cable connections.
The Killin VISTA project aims to remove a total of 7.8 km of overhead line, including 32 steel lattice towers, between the Killin substation and Lix Toll. The project will enhance the character and special qualities of this key gateway location to the National Park by reducing the visual impact of electricity infrastructure on the area.You can see the team’s amazing work for yourself.